Located just under the blue top bar are three tabbed calendar buttons. A resource can use these to locate their allocated jobs and activities within different timeframes:
-
Today.
-
Week.
-
Month.
Both the "Week" and "Month" calendar views display blue dots under days that have allocated jobs or activities.
-
Tapping on a day with a blue dot on it will display the jobs allocated for that day.
-
Tapping on a job or activity card will take the user to the associated details view.
Note
By default, activities, and jobs can be seen for up to three months (90 days) in advance and three months in the past. These values can be changed (reduced) using admin settings. Refer to Admin Settings: Mobile.
When a shift is assigned to a resource, the shift details will appear in Skedulo on the calendar (above the list of job cards for the day)–this is visible in both week and month views.
Note
Shifts are only available for mobile users connected to the new web app.